Project Description
Sector: Road Infrastructure
Client: Constructora Conconcreto S.A.
Bogotá, Colombia
Project details:
The Puente Aranda Grade-Separated Interchange, developed as part of the Calle 13 TransMilenio corridor upgrade project, is one of Bogotá’s most significant road infrastructure projects.
For the foundations of the road bridges, connecting ramps and second-level roundabout, Soletanche Bachy Colombia implemented a deep foundation solution using SB PREFA precast prestressed piles, ensuring high standards of quality, productivity and structural performance.
The project incorporated an innovative impact driving solution with internal drilling, developed to facilitate pile installation in the challenging geotechnical conditions along the corridor and meet the structure’s high load requirements.
This methodology optimized installation rates and enabled the installation of more than 1,000 precast piles, representing over 30,000 linear metres of foundations, providing a reliable, efficient and adaptable solution for large-scale infrastructure projects.
More than 1,000 precast piles and 30,000 linear metres installed for the foundations of one of Bogotá’s most important road interchanges.
Tell us what your project needs.
From a specific geotechnical condition to a challenge requiring several areas of expertise, we can help you identify the right team to discuss possible solutions.

¿Tienes un proyecto?
Cuéntanos tus ideas y construyamos juntos soluciones sólidas, seguras e innovadoras. Nuestro equipo está listo para acompañarte en cada etapa de tu proyecto.